Powering Johan Sverdrup from shore
The first four platforms on this field were completed in 2019, while the fifth will be on stream in 2022.[REMOVE]Fotnote: Equinor website, Johan Sverdrup, https://www.equinor.com/en/what-we-do/johan-sverdrup/phase-2-and-key-milestones.html, accessed 19 November 2021. All are equipped to receive electricity from a facility outside Kårstø north of Stavanger via two parallel transmission cables, each about 200 kilometres long. The alternative to this solution would have been a generating plant fuelled by gas or diesel oil on one of the platforms – with substantial CO2 emissions.
Power from shore was costed in 2018 at about NOK 14 billion.[REMOVE]Fotnote: Proposition no 41 (2018-2019) to the Storting, Utbygging og drift av Johan Sverdrup-feltets andre byggetrinn og anlegg og drift av områdeløsningen for kraft fra land til feltene Johan Sverdrup, Edvard Grieg, Ivar Aasen og Gina Krog: 28. So why was such a large and expensive project was approved and executed?
Arguments for and against
To find the answer, we need to go right back to the 1980s. That was when the Norwegian government became seriously aware of the undesirable effects of excessive emissions of greenhouse gases (GHGs) like CO2. The Kyoto protocol of 1997 brought Norway into an international collaboration aimed at stabilising the amount of GHGs released.
One measure already introduced by then was the country’s CO2 tax, applied from 1991 to petroleum operations on the Norwegian continental shelf (NCS). That made it more expensive for the oil companies to power their platforms with old and inefficient gas-fired units, which released a lot of CO2. Despite this financial disincentive, however, emissions from the oil and gas sector rose by 77.3 per cent from 1990 to 2012.[REMOVE]Fotnote: Statistics Norway, 30 January, 2014, Utslipp til luft, 1990-2012, https://www.ssb.no/natur-og-miljo/statistikker/klimagassn/aar/2014-01-30.
Curbing that increase called for action to cut GHG emissions offshore. One possible option was to scrap gas-fired generating systems and supply platforms with clean hydropower, which accounts for more than 90 per cent of Norway’s electricity supply.[REMOVE]Fotnote: Energifakta Norge Kraftproduksjon, https://energifaktanorge.no/en/norsk-energiforsyning/kraftproduksjon/, accessed 1 July 2022. Various concepts for transmitting power from shore have therefore been debated since the 1990s.
The Norwegian government began ordering oil companies to consider this solution in connection with new field developments or major modification projects as far back as 1996.

A common argument against supplying electricity from land is its high installation cost, particularly on existing facilities. That has been confirmed by a number of reports and studies from government agencies and environmental organisations. as well as by oil companies. The investment can nevertheless be justified if the field concerned has a long producing life and if several fields can be coordinated for such supply.
Another drawback is that a power cut on land might leave platforms without electricity.[REMOVE]Fotnote: https://finansavisen.no/nyheter/energi/2021/11/11/7771269/johan-sverdrup-nede-pa-grunn-av-strombrudd Gas-fired generating capacity must therefore be provided as a reserve. A further objection to power from shore is that any gas not burnt offshore is nevertheless sold for consumption and will cause GHG emissions elsewhere.
Another key argument is that installing power from shore on a number of platforms would increase electricity consumption in Norway. In years with low precipitation, and therefore less water to drive the turbines, that could help create a supply shortfall and higher power prices.
Despite these caveats, a number of NCS fields are now supplied with power from shore.
Troll and Valhall first
The first NCS facility to receive power from shore was Troll A, one of three platforms on this field. Since it came on stream in 1996, this gas production installation has obtained all its electricity from Kollsnes outside Bergen.
A key reason why such a solution was chosen as early as 1990 was Troll A’s relative proximity to land – a mere 69 kilometres. Another important consideration was a desire to reduce the weight and volume of topside equipment. The B and C platforms for oil production are not currently powered from shore, but plans exist to electrify these as well.[REMOVE]Fotnote: Equinor, website, 23 April 2021, Utbyggingsplaner for elektrifisering av Troll Vest overleveres myndighetene, https://www.equinor.com/no/news/archive/20210423-development-plans-troll-west-electrification.
In 2013, Valhall became the first full field on the NCS to operate exclusively on electricity supplied by cable from land. This pioneering project has attracted much attention. A new PH platform was installed in 2011, and the power-from-shore system was officially delivered to Valhall’s operations organisation on 30 January 2012. Valhall PH came on stream in January 2013.
A number of other platforms have become powered from shore since then, and several more are planned (see the table at the end of this article).
Utsira High
Power from shore was also stipulated by a special resolution of the Storting in June 2014 for Johan Sverdrup and several other fields on the Utsira High – Edvard Grieg, Gina Krog and Ivar Aasen.[REMOVE]Fotnote: Proceedings of the Storting, 12 June 2014, https://www.stortinget.no/no/Saker-og-publikasjoner/Publikasjoner/Referater/Stortinget/2013-2014/140612/6. The main justification was that this would reduce GHG emissions since clean hydropower accounts for most Norwegian electricity output.
Animation of electrification on the Utsira High. Photo: Equinor
The Storting’s decision was taken about a year before the plan for development and operation (PDO) of Johan Sverdrup was approved in June 2015.[REMOVE]Fotnote: Proceedings of the Storting, 18 June 2015, https://www.stortinget.no/no/Saker-og-publikasjoner/Saker/Sak/?p=61836. Phase two of the project was approved by special resolution in April 2019.[REMOVE]Fotnote: Proposition no 41 (2018-2019), op.cit, considered by the Storting on 29 April 2019. These decisions were taken after discussing both costs and electricity consumption. A drawback with transmission over long distances is the power losses incurred. To reduce these, direct (DC) rather than alternating (AC) current is used in long submarine cables.[REMOVE]Fotnote: Norwegian Petroleum Directorate, 2020, “Teknologi for kraft fra land”, Kraft fra land til norsk sokkel, https://www.npd.no/fakta/publikasjoner/rapporter/rapportarkiv/kraft-fra-land-til-norsk-sokkel/3—teknologi-for-kraft-fra-land/.
Power from shore has subsequently been approved for the Sleipner and Gudrun fields.
The first power cable supplying the Johan Sverdrup field with electricity from shore was officially commissioned in 2018. A second cable was installed in parallel in 2022. Together, these cables not only supply Johan Sverdrup with power from shore, but also provide electricity to the rest of the Utsira High area: Edvard Grieg and Ivar Aasen from 2022, Gina Krog from 2023, and parts of the Sleipner area, including Gudrun, from 2024.
The increase in Norwegian electricity prices immediately after the North Sea Link interconnector cable with the UK became operational in October 2021 added fuel to the debate on and opposition to powering offshore installations from land.
Demand for Norwegian energy has risen because of the Russia-Ukraine war. Norway is simultaneously in the midst of a “green shift”, with a big move to electric cars to cut CO2 emissions and with ships and aircraft also due to be electrified. All in all, electricity has thereby become more expensive. Developing wind power on land and offshore to generate even more clean energy is controversial because of its interference with nature.
Electrification of the NCS is one of the components in the discussion about what clean energy should be used for in Norway. The arguments for and against power from shore remain valid. It will be up to Norwegian politicians to weigh up these issues and take future decisions.
One alternative to power from shore is offshore wind farms. The licensees on Gullfaks and Snorre resolved in 2019 that these fields should be partly supplied with floating wind power, and the Hywind Tampen farm was commissioned in 2022 and officially inaugurated in 2023.
Table 1: Platforms connected to power from shore
| Platform(s) | Year | Cable Length | MW | AC / DC | Comments |
| Troll A | 1996/2005/2015 | 69 km | 100 / 2 × 41 / 5 × 50 | AC/HVDC | Cables from Kollsnes. Entirely powered from shore; multiple compressors. |
| Ormen Lange | 2007 | 123 km | Subsea facilities. | ||
| Gjøa | 2010 | 98.5 km | 40 | AC | Cable from Mongstad. One gas turbine. |
| Vega | 2010 | 30 km | Cable from Gjøa. | ||
| Valhall | 2013 | 292 km | 78 | HVDC | Cable from Lista. Entirely powered from shore. |
| Goliat | 2016 | 100 km | 75 | AC | Cable from Hyggevatn near Hammerfest. One gas turbine. |
| Martin Linge | 2018 | 163 km | 65 | AC | Cable from Kollsnes. World’s longest subsea AC cable. |
| Johan Sverdrup | 2018 and 2022 | 200 km | 100 / 200 | HVDC | Two cables from Haugsneset near Kårstø. |
| Valhall Flank West | 2019 | Cable from Valhall PH. | |||
| Hod B | 2022 | 13 km | Cable from Valhall PH. | ||
| Edvard Grieg | 2022 | 20 km | 60 | AC | Cable from Johan Sverdrup P2. |
| Ivar Aasen | 2022 | 10 km | 30 | AC | Cable from Edvard Grieg. |
| Gina Krog | 2023 | 62 km | 25 | AC | Cable from Johan Sverdrup P2. One gas turbine. |
| Sleipner (including Utgard, Gungne and Sigyn) | 2024 | 28 km | AC | Cable from Gina Krog. Gas turbines retained. | |
| Gudrun | 2024 | 55 km | Cable from Sleipner A. | ||
| Troll B | 2026 | 85 km | Partly powered from shore. Cable from Kollsnes. | ||
| Troll C | 2026 | 20 km | Entirely powered from shore. Cable from Troll B. | ||
| Draugen | 2027 | 150 km | 80 | Cable from the Straum substation in Åfjord municipality. | |
| Njord | 2027 | 30 km | Cable from Draugen. | ||
| Oseberg Field Centre and Oseberg South | 2027 | 132 km | 105 | Partial electrification. Cable from Kollsnes. |
————————————————————————————————————————————–
Sources
Lorentsen, Kristoffer, Ordering Power from Shore. An STS analysis of electrification of the Norwegian Continental Shelf, https://www.duo.uio.no/bitstream/handle/10852/48537/lorentsen-ordering_power_from_shore.pdf?sequence=1.
Nur, Philip Isaac Rudolfsen, 2017, Kraftkampen. En casestudie av elektrifiseringen av Utsirahøyden, master’s thesis, department of political science, University of Oslo.
Motion from representatives Listhaug, Saudland and Halleland: “Stortinget ber regjeringen stoppe videre elektrifisering av norsk sokkel med strøm fra land”. https://www.stortinget.no/no/Saker-og-publikasjoner/Publikasjoner/Representantforslag/2020-2021/dok8-202021-144s/?m=0.
arrow_backPoland: From service stations to renewable energyAasta Hansteen – small discovery with big pipelinearrow_forward
