Johan Castberg on Stream
Following the high-stakes exploration well in 2011 that encountered oil-bearing Late Jurassic formations, it took well over five years and several different concepts before a Plan for Development and Operation (PDO) was submitted in 2017 and approved in 2018. [REMOVE]Fotnote: https://www.equinor.com/no/news/archive/12jun2018-johan-castberg-pdo-approved
A field of this size, located far from both existing infrastructure and the mainland, requires extensive concept studies to determine the optimal strategy for reservoir development, as well as the type and size of topsides needed to accommodate potential future discoveries in the surrounding area.
The final choice was an FPSO (Floating Production, Storage and Offloading unit), a floating facility that produces, processes (drawing on experience from the operation of Frigg), stores and offloads oil to shuttle tankers for delivery to customers in the global market.
Welding Defects
The hull was constructed in Singapore by Sembcorp Marine, but not without problems. In addition to parts of the construction being affected by the COVID-19 pandemic, technical deficiencies in the structure also led to delays and cost overruns.
In the summer of 2019, Equinor identified unusually high rates of weld defects during a review of the hull, affecting both assembly welds and fabrication welds. [REMOVE]Fotnote: https://www.equinor.com/no/news/archive/202104-welding-quality-johan-castberg-hull
Based on the identified welding defects and the measures implemented to compensate for them, the Petroleum Safety Authority Norway conducted an audit in 2021 [REMOVE]Fotnote: https://www.havtil.no/contentassets/db85bfb8dcf34fe89c69439467c4e243/tilsynsrapport-final.pdf that identified non-conformities related to:
- Inadequate design documentation
· Inadequate fabrication quality
· Use of fracture mechanics analyses as a substitute for independent verification
Among other findings, the authority concluded that, based on the welding defects identified, the overall level of weld defects was likely higher than the industry standard. Consequently, special operational follow-up beyond normal practice should have been in place, according to the Petroleum Safety Authority. Such follow-up had not been planned by Equinor.
In its response, Equinor pointed to several reasons why the welding work had not been satisfactory:
- Insufficient competence among welders and inspectors
· Failure within Equinor to comply with its own work processes and procedures related to risk management, construction management and follow-up
· A follow-up team lacking sufficient personnel with the required experience and expertise, and failure to make use of the company’s specialist resources
Equinor argued that, because the hull was still in dry dock, all defects could be repaired and that the vessel would comply with all requirements before deployment to the field. [REMOVE]Fotnote: https://www.equinor.com/no/news/archive/202104-welding-quality-johan-castberg-hull
The disagreement between the Petroleum Safety Authority (later the Norwegian Ocean Industry Authority) and Equinor persisted, and in June 2024 the former stated:
“Havtil and Equinor have had differing views as to whether it will be possible to bring Johan Castberg up to the same quality level as comparable facilities through inspection and repair during fabrication.” [REMOVE]Fotnote: https://www.havtil.no/tilsyn/tilsynsrapporter/2024/equinor–johan-castberg–konstruksjoner-og-maritime-systemer/
“Should an unwanted incident occur, the damage potential is enormous. In the Barents Sea, the production vessel may encounter ice, polar low-pressure systems and dense fog. It is crucial that this production vessel can withstand the loads it will face in the Barents Sea. Here, Equinor has once again underestimated the complexity and overestimated its own capabilities, as in the U.S. scandal,” stated Bellona chairman Frederic Hauge. [REMOVE]Fotnote: https://www.dn.no/olje/equinor/petroleumstilsynet/olje-og-gass/equinor-far-palegg-av-petroleumstilsynet-for-alvorlige-brudd-pa-castberg-prosjektet/2-1-1018490
During an audit conducted in November 2024 in connection with completion and preparations for safe start-up and operations, no non-conformities were identified, and consent for use was granted in December 2024. [REMOVE]Fotnote: https://www.havtil.no/tilsyn/samtykker/2024/equinor–samtykke-til-bruk-av-johan-castberg/
Important for Northern Norway
The discovery and start-up were important for Equinor’s office in Harstad, which now gained another leg to stand on as an operating organisation, in addition to Norne and Snøhvit. The field is also important for Hammerfest, where the supply base and helicopter base are located.
In June 2025, the field reached plateau production of 220,000 barrels of oil per day and, as of November 2026, accounts for around ten per cent of Norway’s oil production. At a time of declining production volumes, it represents a significant contribution to Norwegian petroleum production.
Only eight months after start-up, it was decided to tie back the Isflak discovery (made in 2021) to Johan Castberg, adding almost 50 million barrels of oil in additional resources. Start-up is planned for late 2028. [REMOVE]Fotnote: https://www.equinor.com/news/will-invest-in-johan-castberg-replenishment
The production vessel produces oil from 30 wells distributed across ten subsea templates, is 313 metres long, and every three to four days a shuttle tanker carrying 700,000 barrels of oil departs for market. The field is the northernmost producing field on the Norwegian continental shelf and the third field in operation in the Barents Sea.