The 2020 Petroleum Tax Relief Package

text_format
In 2022, a record number of Plans for Development and Operation (PDOs) were submitted as a result of the 2020 Petroleum Tax Relief Package adopted during the COVID-19 pandemic. To qualify under the temporary regime, companies had to submit their PDOs before the end of the year.
By Björn Lindberg, Norwegian Petroleum Museum 26 Nov. 2026

In the spring of 2020, the oil price fell dramatically and was, for a brief period, below USD 20 per barrel. This was due to the COVID-19 pandemic and the shutdown of a large number of countries, creating concern among Norwegian politicians about a dramatic fall in investment and the associated major consequences throughout the remainder of the decade.

The government’s response was the 2020 Petroleum Tax Relief Package, which shifted a large share of the investment risk from the oil companies to the state through faster and larger tax deductions.

For projects with PDOs submitted by the end of 2022, companies received an immediate tax deduction for investments that previously had to be depreciated over six years. In addition, companies received an extra deduction (similar to the uplift allowance) in the special tax base.

The purpose was to prevent profitable projects from being postponed or cancelled during the COVID-19 crisis and the oil price collapse, but both industry representatives and politicians later acknowledged that the package was overly generous (Karl Johnny Hersvik and Erna Solberg).

Critics argued that the state was subsidising oil investments and that marginal projects were sanctioned because of the new tax regime. The Petroleum Tax Relief Package could also delay the transition to low-emission industries that the low oil price might otherwise have accelerated.

Because the measure was temporary, companies wishing to qualify for the scheme were under significant time pressure. There is no doubt that several projects were accelerated in order to meet the deadline, and during 2022 a record number of PDOs, as many as 18, were submitted.  [REMOVE]Fotnote: https://www.sodir.no/aktuelt/publikasjoner/rapporter/ressursregnskap/ressursregnskapet-per-31.12.2022/1–ressursregnskapet-for-norsk-kontinentalsokkel-2022/

Figure 1: Number of approved developments on the Norwegian continental shelf. Retrieved from https://www.nrk.no/norge/krisepakke-ble-milliardsluk_-ifolge-rapport_-_-gigantisk-sloseri-1.16869434

Project Operator
Breidablikk Equinor Energy AS
Frosk Equinor Energy AS
Halten Øst Equinor Energy AS
Irpa Equinor Energy AS
Kristin Sør Equinor Energy AS
Verdande Equinor Energy AS
Alve Nord Aker BP ASA
Fenris-Valhall PWP Aker BP ASA
Hod Nyutvikling Aker BP ASA
Idun Nord Aker BP ASA
Symra Aker BP ASA
Tyrving Aker BP ASA
Yggdrasil Aker BP ASA
Ørn Aker BP ASA
Tommeliten A ConocoPhillips Skandinavia AS
Berling OMV Norge AS
Kobra East Gekko (KEG) PGNiG Upstream Norway AS
Dvalin Nord Wintershall Dea Norge AS

Table 1: New developments covered by the temporary tax changes. From Proposition 97 S (2022-2023). [REMOVE]Fotnote: https://www.regjeringen.no/contentassets/bc2fb69527e0473a83600e706b92e486/no/pdfs/prp202220230097000dddpdfs.pdf

Among the large number of PDOs, Equinor had surprisingly few, given that the company is by far the largest operator on the Norwegian continental shelf. Part of the explanation was probably that the company had been fully occupied with the major projects Johan Sverdrup (Phase I and II), Martin Linge, Johan Castberg, and later Wisting. As a result, large parts of the organisation were focused on projects under development rather than progressing new discoveries and prospects towards PDO maturity.

In addition, a few years earlier Equinor had removed exploration from corporate management and merged it with production. This may have contributed to directing resources and effort away from the prospect and discovery portfolio and towards production, which in turn lengthened the runway for bringing projects to PDO maturity.

Aker BP, on the other hand, had a large portfolio of mature development projects that could be accelerated and brought to PDO submission during 2022. [REMOVE]Fotnote: https://www.sodir.no/aktuelt/nyheter/generelle-nyheter/2022/leverte-elleve-utbyggingsplaner/

A significant number of these originated from the merger with Lundin in 2021, which made the company one of the very largest operators on the Norwegian continental shelf. The largest project, Yggdrasil, consisted of several oil and gas fields with a combined resource base of around 700 million barrels of oil equivalent, where both Aker BP and Equinor were operators of licences containing discoveries. For a long time, Equinor and Aker BP planned separate developments, but in 2022 Equinor transferred operatorship for a joint development to Aker BP. [REMOVE]Fotnote: https://www.equinor.com/no/nyheter/overforing-operatorskap-krafla-equinor-aker-bp

 

 