Construction of Statfjord A
The construction of Statfjord A included two major industrial assignments: construction of a concrete substructure and a topside so complicated that no one had done anything like it before.
![](https://i1.wp.com/equinor.industriminne.no/wp-content/uploads/sites/8/2022/03/NOMF-02754.153-scaled.jpg?resize=1248%2C800&ssl=1)
The casting the GBS for Statfjord A took place at Norwegian Contractors in Hinnavågen.
While the topside was being built at Aker Stord Verft.
arrow_backLittle gender equality in the 1970sStorting confirms Statoil’s holdingarrow_forwardFootnotes